ALPHAMIN RESOURCES CORPORATION - Alphamin Announces Q1 EBITDA Guidance of US$52 Million/ Mpama South Commissioning Update

Release Date: 09/04/2024 15:24
Code(s): APH     PDF:  
Wrap Text
Alphamin Announces Q1 EBITDA Guidance of US$52 Million/ Mpama South Commissioning Update


Alphamin Resources Corp.
Continued in the Republic of Mauritius
Date of incorporation: 12 August 1981
Corporation number: C125884 C1/GBL
TSX-V share code: AFM
JSE share code: APH
ISIN: MU0456S00006
("Alphamin" or the "Company")


ALPHAMIN ANNOUNCES Q1 EBITDA GUIDANCE OF US$52 MILLION/ MPAMA SOUTH
COMMISSIONING UPDATE


MAURITIUS – April 9, 2024 – Alphamin Resources Corp. (AFM:TSXV, APH:JSE
AltX)( "Alphamin" or the "Company"), a producer of 4% of the world's mined tin1 from its high
grade operation in the Democratic Republic of Congo, is pleased to provide the following
update for the quarter ended March 2024:

-   EBITDA4 guidance of US$52m, up 156% from the prior quarter
-   Tin sales of 4,126 tonnes, up 102% due to delayed sales the previous quarter
-   Tin production of 3,142 tonnes
-   Mpama South commissioning update

Operational and Financial Summary for the Quarter ended March 20242

                                                                  Quarter ended       Quarter ended
Description                                           Units                                                 Change
                                                                   March 2024         December 2023
Ore Processed                                        Tonnes           109 424               105 510             4%
Tin Grade Processed                                    % Sn              3,83                  3,98            -4%
Overall Plant Recovery                                    %                75                    75             0%
Contained Tin Produced                               Tonnes             3 142                 3 126             1%
Contained Tin Sold                                   Tonnes             4 126                 2 046           102%
EBITDA 3,4 (Q1 2024 guidance)                       US$'000            52 000                20 317           156%
AISC 3, 4 (Q1 2024 guidance)                     US$/t sold            14 785                14 638             1%
Average Tin Price Achieved                            US$/t            26 863                25 157             7%


1
Data obtained from International Tin Association Tin Industry Review 2022 2Information is disclosed on a 100% basis. Alphamin
indirectly owns 84.14% of its operating subsidiary to which the information relates. 3Q1 2024 EBITDA and AISC represent
management's guidance. 4This is not a standardized financial measure and may not be comparable to similar financial measures
of other issuers.See "Use of Non-IFRS Financial Measures" below for the composition and calculation of this financial measure.
Operational and Financial Performance
Contained tin production of 3,142 tonnes for the quarter ended March 2024 was 1% above
that achieved in the previous period. Road conditions have improved during Q1 2024 and as
a result the Company sold 4,126 tonnes of contained tin which incorporated most of the prior
quarter's backlog (Q4 2023: 2,046 tonnes).

EBITDA for Q1 2024 is estimated at US$52m (Q4 2023: US$20m). The EBITDA variance
compared to the prior quarter is attributable to higher tin sales volumes due to the clearance
of most of the Q4 2023 sales backlog and a 7% increase in the tin price. Tin prices are currently
trading at ~US$30,000/t, 12% above prices achieved in Q1 2024. Guidance for AISC per tonne
of tin sold is up 1% from the previous quarter at US$14,785 largely due to increased royalties,
export duties, marketing commissions and net smelter returns, which are calculated with
reference to the higher tin price.

Alphamin's unaudited consolidated financial statements and accompanying Management's
Discussion and Analysis for the quarter ended 31 March 2024 are expected to be released on
or about April 29, 2024.

Mpama South commissioning update

Commissioning of the Mpama South processing plant is progressing well albeit a few weeks
behind our target of tin production from early April 2024. The Company's processing and
engineering team is now part of the final commissioning and the SMPPEI (structural,
mechanical, piping and platework, electrical and instrumentation) contractor's labour
complement is reducing as its activities scale down.

The Mpama South underground development continues on target and ore stockpiles are being
established ahead of the plant. The crusher circuit has produced approximately 5,300 tonnes
of crushed ore for the hot commissioning of the jigging, gravity and fine tin plant areas.
Representatives of the original equipment manufacturer of the crusher are on site attending to
the replacement of a failed mechanical unit. The mine has replacement spares for this unit
while the matter is being addressed.

1. Run of mine stockpile ahead of the crushing plant
2. Crushing plant and crushed ore stockpile
3. Jigging area
4. Gravity processing facility, fine tin plant and concentrate drying
Liquidity and dividend update


The Company's cash position increased to US$53,5m as at 31 March 2024 (Net Debt4:
US$28m) from US$7,2m at the end of the prior quarter (31 December 2023 Net Debt:
US$73m).

As previously reported, the Company intends to make a final FY2023 dividend decision in April
2024 to align with the timing of holding the annual general meeting of Alphamin Bisie Mining
SA (ABM), the Company's DRC operating subsidiary, to approve ABM's annual financial
statements and to consider the declaration of a dividend for distribution to its shareholders.
The ABM annual general meeting has been scheduled for 24 April 2024. Alphamin Resources
has scheduled a board meeting for 26 April 2024 to consider a final FY2023 dividend.

Qualified Person

Mr. Clive Brown, Pr. Eng., B.Sc. Engineering (Mining), is a qualified person (QP) as defined in
National Instrument 43-101 and has reviewed and approved the scientific and technical
information contained in this news release. He is a Principal Consultant and Director of Bara
Consulting Pty Limited, an independent technical consultant to the Company.
_________________________________________________________________________________________


FOR MORE INFORMATION, PLEASE CONTACT:

Maritz Smith
CEO
Alphamin Resources Corp.
Tel: +230 269 4166
E-mail: msmith@alphaminresources.com

9 April 2024

JSE Sponsor
Nedbank Corporate and Investment Banking, a division of Nedbank Limited



CAUTION REGARDING FORWARD LOOKING STATEMENTS
Information in this news release that is not a statement of historical fact constitutes forward-
looking information. Forward-looking statements contained herein include, without limitation,
statements relating to EBITDA and AISC guidance for Q1 2024; commissioning of the Mpama
South processing plant; progress regarding underground development of the Mpama South
project and the timing of the expected consideration of a final FY2023 dividend. Forward-
looking statements are based on assumptions management believes to be reasonable at the
time such statements are made. There can be no assurance that such statements will prove
to be accurate, as actual results and future events could differ materially from those anticipated
in such statements. Accordingly, readers should not place undue reliance on forward-looking
statements. Although Alphamin has attempted to identify important factors that could cause
actual results to differ materially from those contained in forward-looking statements, there
may be other factors that cause results not to be as anticipated, estimated or intended. Factors
that may cause actual results to differ materially from expected results described in forward-
looking statements include, but are not limited to: uncertainties regarding completion of the
commissioning of the Mpama South processing plant and the availability of ore at expected
quantities and grades, uncertainties regarding global supply and demand for tin and market
and sales prices, uncertainties with respect to social, community and environmental impacts,
uninterupted access to required infrastructure and third party service providers, adverse
political events and risks of security related incidents which may impact the operation or safety
of its people, uncertainties regarding the legislative requirements in the Democratic Republic
of the Congo which may result in unexpected fines and penalties, impacts of the global Covid-
19 pandemic or other health crises on mining operations and commodity prices as well as
those risk factors set out in the Company's annual Management Discussion and Analysis and
other disclosure documents available under the Company's profile at www.sedarplus.ca.
Forward-looking statements contained herein are made as of the date of this news release
and Alphamin disclaims any obligation to update any forward-looking statements, whether as
a result of new information, future events or results or otherwise, except as required by
applicable securities laws.


Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined
in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.


USE OF NON-IFRS FINANCIAL PERFORMANCE MEASURES
This announcement refers to the following non-IFRS financial performance measures:

EBITDA

EBITDA is profit before net finance expense, income taxes and depreciation, depletion, and
amortization. EBITDA provides insight into our overall business performance (a combination
of cost management and growth) and is the corresponding flow driver towards the objective of
achieving industry-leading returns. This measure assists readers in understanding the ongoing
cash generating potential of the business including liquidity to fund working capital, servicing
debt, and funding capital expenditures and investment opportunities.

This measure is not recognized under IFRS as it does not have any standardized meaning
prescribed by IFRS and is therefore unlikely to be comparable to similar measures presented
by other issuers. EBITDA data is intended to provide additional information and should not be
considered in isolation or as a substitute for measures of performance prepared in accordance
with IFRS.

NET DEBT

Net debt is defined as total current and non-current portions of interest-bearing debt and lease
liabilities less cash and cash equivalents.


AISC

AISC is the cash cost to produce a tonne of contained tin plus the capital sustaining costs to
maintain the mine, processing plant and infrastructure and the off-mine costs to sell a tonne of
contained tin. This measure includes cash costs and capital sustaining costs divided by tonnes
of contained tin produced plus off-mine costs to transport and sell a tonne of contained tin. All-
In Sustaining Cost per tonne does not include depreciation, depletion, and amortisation,
reclamation, borrowing costs and exploration expenses.
Sustaining capital expenditures are defined as those expenditures which do not increase
payable mineral production at a mine site and excludes all expenditures at the Company's
projects and certain expenditures at the Company's operating sites which are deemed
expansionary in nature.

Date: 09-04-2024 03:24:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Share This Story