PAN AFRICAN RESOURCES PLC - Operational Update for the half-year ended December 2025 (H1FY26) and Proposed Initiation of Interim Dividend

Release Date: 26/01/2026 09:00
Code(s): PAN PARS02 PARS03     PDF:  
Wrap Text
Operational Update for the half-year ended December 2025 (H1FY26) and Proposed Initiation of Interim Dividend

Pan African Resources PLC                                  Pan African Resources Funding Company
(Incorporated and registered in England and Wales          Limited
under the Companies Act 1985 with registered               Incorporated in the Republic of South Africa
number 3937466 on 25 February 2000)                        with limited liability
Share code on LSE: PAF                                     Registration number: 2012/021237/06
Share code on JSE: PAN                                     Alpha code: PARI
ISIN: GB0004300496
ADR ticker code: PAFRY
("Pan African Resources" or the "Company" or the
"Group")


OPERATIONAL UPDATE FOR THE HALF-YEAR ENDED DECEMBER 2025 (H1FY26) AND
PROPOSED INITIATION OF INTERIM DIVIDEND

Pan African is pleased to provide its shareholders and noteholders with an operational update for the half
year ended 31 December 2025 (Reporting Period) as well as to announce the initiation of an interim
dividend to be approved by the Company's board of directors (Board) together with the H1FY26 results.

KEY FEATURES
    •       INCREASE IN GOLD PRODUCTION OF 51% TO 128,296OZ (H1FY25: 84,705OZ)
    •       FURTHER PRODUCTION INCREASES EXPECTED IN H2FY26, ON TRACK TO MEET FULL
            YEAR PRODUCTION GUIDANCE
    •       SUBSTANTIALLY DE-GEARED BALANCE SHEET - REDUCTION IN NET DEBT OF MORE
            THAN 65%
    •       INITIATION OF INTERIM DIVIDEND PROPOSED - ZA12 CENTS PER SHARE
    •       DEFINITIVE FEASIBILITY STUDY SOWETO CLUSTER PROJECT - EXPECTED TO BE
            COMPLETED BY JUNE 2026

SAFETY
    •       Improvement in overall Group safety performance

        o     Total Recordable Injury Frequency Rate (TRIFR) improved substantially to 4.74 (H1FY25:8.25)
              per million-man hours
        o     Lost Time Injury Frequency Rate (LTIFR) improved to 1.22 (H1FY25: 1.54) per million-man
              hours.

PRODUCTION
    •       Increase in gold production of 51% to 128,296oz (H1FY25: 84,705oz), with the Group on track to
            meet full year production guidance range of between 275,000oz and 292,000oz
               o   Production at Evander operations improved substantially by 87% to 21,640oz (H1FY25:
                   11,551oz), with the subvertical hoisting shaft operating at capacity and mining in the high-
                   grade Kinross Channel of the Kimberley Reef. Production in H2FY26 is expected to
                   increase further with higher mined tonnages

               o   Elikhulu achieved excellent results, with production increasing by 14% to 29,450oz
                   (H1FY25: 25,725oz)
            o   Mogale Tailings Retreatment (MTR) operations at steady state following ramp-up in FY25,
                with production of 21,729oz, approximately 10% lower than expected, as a result of mining
                grades and recoveries impacted by the current mining area

                    -   MTR expansion to 1,000ktpm was successfully commissioned in December 2025,
                        with increased capacity and improved recoveries expected to increase gold
                        production in H2FY26. Going forward annualised production from MTR is
                        expected to be between 55-60kozpa

            o   Barberton Mines underground production increased by 5% to 32,774oz (H1FY25:
                31,142oz) and BTRP production remained stable at 7,143oz (H1FY25: 7,544oz)

            o   Tennant Mines achieved steady state throughput, with production of 15,560oz (including
                gold equivalent ounces from the sale of copper concentrate). Production in H2FY26 is
                anticipated to increase to approximately 30,000oz as higher-grade ore from open pits
                replace lower grade feed from the Crown Pillar Stockpile (CPS). The average expected
                recovered mining grade in H2FY26 is planned at 2.22g/t (H1FY26:1.15g/t).

FINANCIAL
   •   The Group has now substantially de-geared its balance sheet, with reduction in net debt of more
       than 65% to US$49.9m, compared to US$150.5m in June 2025

            o   Given the prevailing high gold prices, the Group expects to be fully de-geared (in terms of
                net debt) by the end of February 2026. This is despite the payment of a record final dividend
                to shareholders in December 2025

   •   All in sustaining cost (AISC) of production for H1FY26 is expected in the range of US$1,825/oz -
       US$1,875/oz at US$/ZAR17.37, (FY26 full year guidance: US$1,525/oz to US$1,575/oz at
       US$/ZAR18.50) negatively impacted by:

            o   the strengthening of the US$/ZAR exchange rate by 6.1% to US$17.37, with an impact of
                approximately US$115/oz

            o   the increase in employee share-based payment expenses, as a result of an increase of
                more than 140% in the Company share price from ZAR11.09 (GBp45.75) at 30 June 2025
                to ZAR26.98 (GBp121.00p) at 2 January 2026 (approximately US$80/oz)

            o   third party material processed at the Evander and MTR operations during the period
                contributing to higher costs, as well as increased royalty payments due to the higher gold
                price received

   •   Increased gold production guided for H2FY26 is anticipated to reduce unit costs of production.

PROPOSED INTERIM DIVIDEND FOR THE SIX MONTHS ENDED 31 DECEMBER 2025

   •   Interim cash dividend of ZA12 cents per share (or US0.74488 cents per share at an indicative
       exchange rate of US$/ZAR:16.11 or 0.54745 pence per share at an indicative exchange rate of
       GBP/ZAR:21.92) is intended to be approved by the Board together with the interim results for the
       six months ended 31 December 2025. Further information regarding the formal declaration of the
       proposed interim dividend as required in terms of the JSE Listings Requirements, including the
       salient dates, will be communicated with the release of the Group's interim results on 18 February
       2026.

FUTURE PRODUCTION GROWTH

        •   A feasibility study to process the Group's Soweto Cluster Tailings Storage Facilities (Soweto
            TSFs) was successfully completed during the Reporting Period (announced on SENS and RNS
            on 27 November 2025). An integrated 600ktpm Soweto Tailings Retreatment (STR) circuit at
            MTR was identified as the preferred option to process the Soweto TSFs, due to a significantly
            lower upfront capital requirement, a shorter construction period, reduced permitting obligations
            and superior financial returns. This option will also benefit from synergies with the existing MTR
            plant and operational infrastructure

                 o   The Definitive Feasibility Study for this option is expected to be completed by June
                     2026, with a final Board decision to commence project construction shortly thereafter

                 o   Anticipated construction period of approximately 24 months

                 o   Expected annual gold production of 30-35koz for approximately 15 years at an all-in-
                     sustaining-cost (AISC) of between US$1,000/oz and US$1,200/oz, which will increase
                     production from the MTR complex to approximately 100kozpa, once construction is
                     complete

    •   At Tennant Mines, the earn-in exploration joint venture with ASX listed Emmerson Resources on
        which the White Devil project and others are located was successfully concluded during September
        2025

            o    Ongoing exploration on the Group's wholly owned Mining Leases at Nobles, Juno and
                 Warrego confirmed extensions to the known mineralised zones. Additionally, regional
                 exploration programmes comprising magnetotelluric geophysical surveys and remote
                 sensing has identified more than 10 new prospective targets for exploration.

ENVIRONMENTAL, SOCIAL AND GOVERNANCE UPDATES

    •   Following the completion of positive feasibility studies for the 20MW Evander Mines' phase 2 solar
        plant expansion, total solar generation capacity at Evander will be expanded from 10MW to 30MW.
        A contractor has been appointed and construction of the additional capacity is expected to
        commence by June 2026

    •   In July 2025, site work commenced on phase 2 of the 3ML/day Evander water treatment plant, with
        first water expected in late February 2026. At MTR, construction of a 3ML/day water treatment plant
        to treat acid mine drainage water commenced in November 2025. This plant is expected to be
        commissioned in May 2026 and will produce potable water to meet the requirements of the MTR
        processing plant

    •   The MTR operation was awarded the 'Best ESG Initiative by a Mining Company' at the international
        Resourcing Tomorrow conference held in December 2025, where competing entries included
        projects from other international mining groups. The judges recognised the immediate positive
        impacts of Pan African's activities on the environment and local communities, following years of
        neglect in the area.

Pan African Resources CEO Cobus Loots commented:

"Pan African's safety, operational and financial performance in the first half of the financial year, together
with the boon of record gold prices, has positioned us to deliver outstanding results for the full year. During
the reporting period the Group de-geared its balance sheet and is also now further boosting cash returns
to shareholders, with our board set to approve an attractive proposed interim dividend payment.
The half year results demonstrate the success of our strategy of focusing on high-margin, long-life tailings
retreatment operations and also the acquisition of the very prospective Tennant Mining in Australia. We
also wish to commend the Evander management team for the successful turnaround of the underground
operation, with further improvements expected in the period ahead.

Despite our continued focus on cost control, all-in sustaining unit costs were higher than guided for the
reasons detailed in this release, we believe the expected increased gold production in H2 of the financial
year will assist with reducing unit costs.

We are excited about the further production growth opportunities within our asset portfolio. Pan African is
capitalising on the very favourable current environment to position the Group to continue "Mining for a
Future" for many more years.

We look forward to presenting our interim results, including details on our prospects and initiatives, on 18
February 2026."

The information contained in this announcement is the responsibility of the Company's Board and has not
been reviewed or reported on by the Group's external auditors.

Johannesburg

26 January 2026

For further information on Pan African, please visit the Company's website at

www.panafricanresources.com

 Corporate information
 Corporate Office                                       Registered Office
 The Firs Building                                      107 Cheapside, 2nd Floor
 2nd Floor, Office 204                                  London, EC2V 6DN
 Corner Cradock and Biermann Avenues                    United Kingdom
 Rosebank, Johannesburg                                 Office: + 44 (0)20 3869 0706
 South Africa                                           jane.kirton@corpserv.co.uk
 Office: + 27 (0)11 243 2900
 info@paf.co.za

 Chief Executive Officer                                Financial Director and debt officer
 Cobus Loots                                            Marileen Kok
 Office: + 27 (0)11 243 2900                            Office: + 27 (0)11 243 2900

 Head: Investor Relations                               Website: www.panafricanresources.com
 Hethen Hira
 Tel: + 27 (0)11 243 2900
 E-mail: hhira@paf.co.za

 Company Secretary                                      Joint Broker
 Jane Kirton                                            Ross Allister/Georgia Langoulant
 St James's Corporate Services Limited                  Peel Hunt LLP
 Office: + 44 (0)20 3869 0706                           Office: +44 (0)20 7418 8900

 JSE Sponsor & JSE Debt Sponsor                        Joint Broker
 Ciska Kloppers                                        Thomas Rider/Nick Macann
 Questco Corporate Advisory Proprietary                BMO Capital Markets Limited
 Limited                                               Office: +44 (0)20 7236 1010
 Office: + 27 (0) 63 482 3802
                                                       Joint Broker
                                                       Matthew Armitt/Jennifer Lee
                                                       Joh. Berenberg, Gossler & Co KG
                                                       (Berenberg)
                                                       Office: +44 (0)20 3207 7800

Date: 26-01-2026 09:00:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.