ACSION LIMITED - Contruction Contract Constituting a Small Related Party Transaction

Release Date: 11/11/2024 16:28
Code(s): ACS     PDF:  
Wrap Text
Contruction Contract Constituting a Small Related Party Transaction

ACSION LIMITED
Incorporated in the Republic of South Africa
(Registration number 2014/182931/06)
Share code: ACS  ISIN: ZAE000198289
("Acsion" or the Group")


CONSTRUCTION CONTRACT CONSTITUTING A SMALL RELATED PARTY TRANSACTION


1. Introduction

   Shareholders are advised that on 8 November 2024, Hey Joe Proprietary Limited ("Hey Joe"), a wholly
   owned subsidiary of Acsion, concluded a construction contract with K. Anastasi Projects Proprietary
   Limited ("KAP") appointing KAP as its principal contractor for the construction of 69 new hotel units on
   the property owned by Hey Joe ("Property") for a cash amount of R87 536 248.20 inclusive of a
   contingency allowance, as set out in paragraph 3.1 below ("Construction Contract").

   KAP, which trades in the construction sector, is beneficially owned by the chief executive officer of
   Acsion, Mr Kiriakos Anastasiadis, and his family through a trust structure and therefore the Construction
   Contract is deemed a small related party transaction for Acsion in terms of the Listings Requirements
   of the JSE Limited ("JSE").

2. Rationale

   The Hey Joe Brewing Company is a Belgian inspired tap room, restaurant and brewing company
   situated on the Property located in Franschhoek, Western Cape.

   The construction of the new hotel units on the Property aligns with the Group's long-term strategic
   objective of delivering Net Asset Value growth through the execution of its long-term expansion,
   diversification and development plans.

   KAP was appointed as principal contractor following a closed tender process managed by an
   independent quantity surveying firm which has been appointed as the principal agent. The appointment
   was based on a market related price for the works, KAP's long-standing reputation in the construction
   industry and its proven track record in successfully executing projects of a similar size and nature.

   Pursuant to the Construction Contract, as principal contractor on the project, KAP will be responsible
   for planning, leading and executing the general building works as well as overseeing and managing
   other direct contractors and subcontractors involved in the project.

3. Construction Contract

   3.1   Contract Value and settlement

         The value of the Construction Contract, of R87 536 248.20, including the contingency allowance
         ("Contract Value"), will be settled by way of cash payments by Hey Joe of such amounts as are
         certified in the monthly interim payment certificates issued by the principal agent in terms of the
         Construction Contract, within 14 (fourteen) calendar days of the date of presentation thereof.

   3.2   Fairness Opinion

         In terms of paragraph 10.7 of the Listings Requirements, the Construction Contract constitutes a
         small related party transaction for Acsion.

         A small related party transaction is not subject to shareholder approval, provided an independent
         expert has confirmed that the terms thereof are fair as far as shareholders are concerned. The
         board of directors of Acsion ("Board") has appointed Merchantec Proprietary Limited
         ("Merchantec") to provide the Board with a fairness opinion prepared in accordance with
         Schedule 5 of the Listings Requirements ("Fairness Opinion"). Merchantec has concluded that
         the terms of the Construction Contact are fair insofar as the shareholders of Acsion are
         concerned, and a copy of its Fairness Opinion in this regard has been approved by the JSE.

         As required in terms of paragraph 10.7(c) of the Listings Requirements, the Fairness Opinion is
         available for inspection at Acsion's registered office, Anaprop Offices, Mall@Reds Cnr Hendrik
         Verwoerd Drive and Rooihuiskraal Drive, Centurion, 0157, and/or through a secure electronic
         manner at the election of the person requesting the inspection, for a period of 28 days from the
         date of this announcement. Shareholders who wish to view the Fairness Opinion should send
         their request to the Company Secretary at michael@mwrk.co.za, who will facilitate access to
         same.


Johannesburg
11 November 2024

Sponsor
Merchantec Capital

Date: 11-11-2024 04:28:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.